International Sourcing Project Case Study
CTS Case Study #: 04102
Unit Size: 8’5″ L x 5′ W x 7’6″ H
Unit Weight: 3,600 LBS
Flow Rate: 56 GPM
Opportunity: All electrical equipment and instruments were required to be purchased directly from Japan and include the certificate of “Ministry of Labour The Research Institute of Industrial Safety, Japan.”
Solution: CTS worked with suppliers in Japan to source all components directly from Japan. These components were installed on the skid and the skid was shipped to a client in Kobe, Japan. The state of Pennsylvania has representatives covering over 70 different countries that can help coordinate component sourcing.